Q1 Which of the following criteria on test progress would enable the business to determine a likely `go live’ date?

(i) Number of tests planned versus number of tests executed

(ii) Number of high priority efects outstanding

(iii) The test team’s timesheets in order to show how much effort has been devoted to testing

(iv) Number of tests passed and number failed

(v) Number of defects found in each development area

(vi) The rate at which defects are being found

[K2] 1 credit

A. (ii), (iii), (iv)
B. (i), (iii), (v)
C. (i), (ii), (vi)
D. (iv), (v), (vi)

Answer: C

Q2
As a test analyst you are involved in the early stages of an acceptance test for a Product Data Management system. You are asked to write test designs and test cases based on use cases. An early version of the system is also already available. It is a known fact that on the implementation level many things will change (including the user-interface). The tests will be carried by end-users with much domain knowledge who have also been involved in the project defining the user requirements and reviewing documentation.

What is the BEST option regarding the level of detail and documentation required for test cases in the project?

[K4] 3 credits

A. Detailed concrete test cases since many re-runs of the tests are expected
B. Logical test cases supported by concrete test cases to allow for traceability and enable future changes
C. Concrete test cases only since the end-users have extensive domain knowledge
D. Logical test cases only since the end-user have extensive domain knowledge and many changes are expected thus reducing testware maintenance effort

Answer: D

CTAL-TA_Syll2012 Prüfungsfragen, CTAL-TA_Syll2012 Examensfragen ISTQB Certified Tester Advanced Level – Test Analyst (Syllabus 2012) (ICND2 v3.0)https://www.it-pruefungen.de/CTAL-TA_Syll2012.htm

Q3
As a test analyst you are gathering data to support accurate metrics. Which of the following metrics would be MOST appropriate to use to monitor product quality?

[K2] 1 credit

A. Defects found versus defects expected
B. Tests run and tests passed
C. Test resources spent versus budget
D. Compliance to entry criteria
E. Product risks outstanding and new risks introduced

Answer: A,B,E

Q4
Which of the following tasks and responsibilities do NOT belong to that of a test analyst in the context of evaluating exit criteria and reporting?

[K2] 1 credit

A. The test analyst should be able to use the reporting tools
B. The test analyst is responsible for supplying accurate information
C. The test analyst will contribute to the final report at the end of the testing
D. The test analyst should write final test reports objectively

Answer: D

Q5
What is the MOST important reason why test conditions should be understandable by stakeholders?

[K2] 1 credit

A. They should be able to review the test conditions and provide feedback to the test analyst
B. They should be able to use them as a basis for designing test cases
C. They should be able to use them to establish traceability to requirements
D. Test documentation should always be understandable by all stakeholders

Answer: A

Prüfungsvorbereitung Studienmaterial CTAL-TA_Syll2012 deutsch ISTQB Certified Tester Advanced Level – Test Analyst (Syllabus 2012) www.it-pruefungen.ch

 

Prüfungsvorbereitung CTFL-001, Studienmaterial CTFL-001

Prüfungsvorbereitung CTFL-001, Studienmaterial CTFL-001 deutsch ISTQB Certified Tester Foundation Level www.it-pruefungen.ch

Topic 1, Scenario 1 “Medical Domain”

You are working as a test manager in the medical domain leading a team of system testers. You are currently working on a major release of the product which gives customers many new features and resolves a number of problem reports from previous releases.

Q1
You are about to release a test progress report to a senior manager, who is not a test specialist. Which of the following topics should NOT be included in the test progress report?

A. Product risks which have been mitigated and those which are outstanding.
B. Recommendations for taking controlling actions
C. Status compared against the started exit criteria
D. Detailed overview of the risk-based test approach being used toensure the exit criteria to beachieved

Answer: D

Q2
Explain how the above mentioned report may differ from a report that you produce for the project manager, who is a test specialist Select TWO items from the following options that can be used to report to the project manager and would not be included in a report to senior management.

A. Show details on effort spent
B. List of all outstanding defects with their priority and severity
C. Give product risk status
D. Show trend analysis
E. State recommendations for release

Answer: A,B

Q3
Consider the typical objectives of testing. Which of the following metrics can be used to measure the effectiveness of the testing process in achieving one of those objectives?

A. Average number of days between defect discovery and resolution
B. Percentage of requirements covered
C. Lines of code written per developer per day
D. Percentage of test effort spent on regression testing

Answer: B

IT-Prüfungen CTFL-001 ISTQB Certified Tester Foundation Level https://www.it-pruefungen.ch/CTFL-001.htm

Q4
You have been given responsibility for the non-functional testing of a safety-critical monitoring & diagnostics package in the medical area. Which of the following would you least expect to see addressed in the test plan?

A. Availability
B. Safety
C. Portability
D. Reliability

Answer: C

Q5
Since the system is in the medical domain and therefore in the safety critical area, testing needs to be rigorous and evidence is required that the system has been adequately tested. Identify THREE measures that would typically be part of the test approach in this domain and which are not always applicable in other domains!

A. High level of documentation
B. Failure Mode and Effect Analysis (FMEA) sessions
C. Traceability to requirements
D. Non-functional testing
E. Master test planning
F. Test design techniques
G. Reviews

Answer: A,B,C

CTFL-001 Prüfungsfragen ISTQB Certified Tester Foundation Level www.it-pruefungen.ch

Hallo Welt!

Willkommen zur deutschen Version von WordPress. Dies ist der erste Artikel. Du kannst ihn bearbeiten oder löschen. Um Spam zu vermeiden, geh doch gleich mal in den Pluginbereich und aktivier die entsprechenden Plugins. So, und nun genug geschwafelt – jetzt nichts wie ran ans Bloggen!